NTBCC minutes – Monday 11 January 2021

Minutes of New Town & Broughton Community Council’s ordinary meeting, held via Zoom, on Monday 11 January 2020 at 7pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 25 June 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 25 June 2020 at 5:30pm Continue reading

NTBCC minutes – Monday 16 December 2019

Minutes of New Town & Broughton Community Council’s ordinary meeting, held in the Garden Room, Broughton St Mary’s church, Bellevue Crescent on Monday 16 December 2019 at 7.30pm Continue reading

NTBCC minutes – Monday 9 September 2019

Minutes of New Town & Broughton Community Council’s ordinary meeting, held in Drummond Room, Broughton St Mary’s church, Bellevue Crescent on Monday 9 September 2019 at 7.30pm

Actions and decisions are red italic underlined. nem con means that no-one spoke or voted against a decision.

In the chair’s absence at the start of the meeting, the vice-chair chaired the start of the meeting (items 1, 2, 3, 5 and 6).

1 Attendance and apologies for absence

Susanna Beaumont NTBCC Carol Nimmo NTBCC Chair
Judy Conn NTBCC secretary Richard Price NTBCC Planning convener
Stephen Hajducki NTBCC Sheila Warnock NTBCC
Simon Holledge NTBCC Communications convener Alan Welsh NTBCC
Stuart McAllister NTBCC Alllan Jack NTBCC Transport convener
Jack Hugh NTBCC Alan Macintosh Broughton Spurtle
Susan Macinnes NTBCC ~35 residents

1.1 Apologies for absence

Jonathan Finn NTBCC treasurer Cllr Amy McNeese-Mechan Leith walk ward
Chrissie Ross NTBCC treasurer Cllr Joanna Mowat City Centre ward
Deidre Brock MP

Hal Osler

Edinburgh North and Leith

Inverleith

Continue reading

Notification of essential works Bellevue area Edinburgh – Update 18 August

(adapted from an email from SGN)

Dear everyone

I’d like to give you a brief update on our work in the Bellevue area which continues to progress well.

As you are aware we’re carrying out our work in five phases to help minimise disruption as much as possible. Phase three of our work will start in Bellevue on Monday 2 September. For approximately four weeks, both Bellevue and Bellevue Crescent will be closed and parking restrictions will be in place. If possible, we’ll keep some parking spaces available. Signed diversion routes will be in place for motorists and commuters.

We’ll be working Monday to Friday between 7am and 4pm, and extended hours and weekends when possible. Local residents will receive a letter in the next few days.

We know that this is a busy area and wish to assure everyone that work will progress as quickly as possible and we’ll be doing everything we can to limit delays and disruption.

Thank you for your patience and continued support.

Kind regards

Caroline

Caroline Lawrie, Stakeholder and Community Manager
T: +44 (0)131 469 1701 (: 31701)
M: +44 (0)7747 7577 99
E: caroline.lawrie@sgn.co.uk
SGN, Axis House, 5 Lonehead Drive, Newbridge, Edinburgh,EH28 8TG
sgn.co.uk
Find us on Facebook and follow us on Twitter: @SGNgas

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

NTBCC ordinary meeting minutes – Monday 13 May 2019

Minutes of New Town & Broughton Community Council’s ordinary meeting, held in Drummond Room, Broughton St Mary’s church, Bellevue Crescent on Monday 13 May 2019 at 7.30pm Continue reading