Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 26 November 2020 at 5:30pm Continue reading
Dalmeny St
Community Councils Together on Trams/Trams Team meeting, 01 October 2020
Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 1 October 2020 at 5:30pm Continue reading
Trams to Newhaven – latest newsletter
Here’s the latest (text only). There’s little in this issue about NTBCC-land but the content may well of interest.
Leith Walk
Site investigation, excavation works and surface water drainage installation is continuing from London Road to Crown Street.
Pilrg Street to Dalmeny Street
This section of works has been handed back to our Infrastructure & Systems Contractor, SFN, who will commence the main tram infrastructure works.
Newhaven
Main tram infrastructure works are continuing in this area.
Ocean Terminal
This area is one of the first section of works that was handed back to our Infrastructure & Systems Contractor, SFN. This has seen the commencement of the main tram infrastructure works in this area. The works are progressing well with the much-anticipated track laying works, scheduled to commence in November 2020. Further updates will follow over the coming weeks on our digital platforms.
Constitution Place to Baltic Street
Works are progressing well in this area with the section of works being handed back to the Infrastructure & Systems Contractor, SFN. The Tower Street junction remains closed with further updates expected to follow in the coming weeks.
See this newsletter and all previous ones – with pictures – on Trams to Newhaven website.
Subscribe to TTN newsletters on another TTN web-page.
Community Councils Together on Trams/Trams Team meeting, 27 August 2020
Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 27 August 2020 at 5:30pm Continue reading
Community Councils Together on Trams/Trams Team meeting, 25 June 2020
Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 25 June 2020 at 5:30pm Continue reading
Main construction start – Trams to Newhaven
(Copied from an email from Trams to Newhaven)
The main construction works for the Edinburgh’s Trams to Newhaven project will start from Monday 15 June 2020 in line with the Scottish Government’s Phase 2 ‘soft start to site works (only where physical distancing can be maintained).
Work on the project was stopped at the end of March to comply with Government guidance and to protect the safety of workers and residents during the coronavirus outbreak.
Following the First Minister’s announcement on 21 May of a phased return for construction sites, plans have been drawn up in line with Scottish Government safety guidelines and industry best practice to ensure the safety of workers and the public. At the briefing on 28 May the First Minister confirmed that site preparation could begin and, following the announcement today, main construction works can now start. This will encompass the existing sites on Lindsay Road, Melrose Drive and Constitution Street which will start from Monday 15 June. In addition, main construction works on Leith Walk from Elm Row to Crown Place will start on Monday 22 June.
In advance of this some preparatory works on Leith Walk will start on Monday 15 June 2020 ahead of the installation of traffic management which will begin on the evening of Friday 19 June and be operational from 5am on Saturday 20 June 2020 including Lothian Bus diversions. All traffic management arrangements are made in consultation with key partners in the city, including blue light services and public transport providers, through the Traffic Management Review Panel and are continuously monitored and reviewed to ensure they work as effectively as possible.
All works will be carried out through physical distancing and additional measures to protect workers’ health will include daily briefings, continuous on-site inspections and health and safety ‘ambassadors.’ The numbers of workers on-site will be kept to a minimum and a large proportion of the project office staff will continue to work from home. While physical distancing will be a key principle of construction working, workers will also have access to personal protection equipment (PPE) which they may choose to wear as an additional precaution if they wish. It should be noted that it may take time for the sites to become fully operational.
The logistic hubs at the Mitchell Street, Foot of the Walk, Dalmeny Street, Albert Street and Montgomery Street will re-open on Monday 22 June to support local businesses with deliveries and despatches. All communal bins that are currently situated on Leith Walk will be moved to the side streets.
If you have any queries please do not hesitate to get in contact.
Chris Wilson
For information
The Scottish Government’s phased approach to construction details six key phases to ensure work is carried out in a safe way. These are:
- Phase 0: Planning
- Phase 1: Covid-19 Pre-start Site preparation
- Phase 2: ‘Soft start’ to site works (only where physical distancing can be maintained)
- Phase 3: Steady state operation (only where physical distancing can be maintained)
- Phase 4: Steady state operation (where physical distancing can be maintained and/or with PPE use)
- Phase 5: Increasing density/productivity with experience
More detail on carriageway resurfacing works – Summer 2019/20
Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.
Location | Planned Start Date | Estimated Duration | Work Detail |
Broughton Street | 28-May + 22 Aug | 4 weeks + 2 weeks | Pedestrian crossing upgrade + carriageway resurfacing |
Albany Street | 03-Jun | 1 week | Carriageway resurfacing |
Hopetoun Street | 07-Jun | 2 days | Carriageway resurfacing |
Academy Street | 11-Jun | 1 week | Overlay setts |
Dalmeny Street | 17-Jun | 10 days | Carriageway resurfacing, overlay setts and minor footway works |
East Hermitage Place | 26-Jun | 3 days | Carriageway resurfacing |
Portland Place | 28-Jun | 1 week | Carriageway resurfacing |
McDonald Road | 01-Jul | 10 days | Footway widening and carriageway patching |
Easter Road/Duke Street | 01-Jul | 8 weeks | Junction redesign |
East London Street | 02-Jul | 7 weeks | Pedestrian crossing upgrade and carriageway resurfacing |
Duncan Place | 10-Jul | 2 weeks | Carriageway resurfacing and minor footway works |
Great Junction Street | 10-Jul | 1 week | Carriageway resurfacing |
Gordon Street | 02-Aug | 1 week | Carriageway resurfacing |
Bonnington Road | 08-Aug | 3 weeks | Carriageway resurfacing |
Ocean Drive | 08-Aug | 3 days | Carriageway resurfacing |
North Leith Sands | 13-Aug | 1 week | Carriageway resurfacing and minor footway works |
Newhaven Road | 26-Aug | 2 weeks | Carriageway resurfacing |
Annandale Street | 29-Aug | 7 weeks | New pedestrian crossings and carriageway resurfacing |
Broughton Road | 05-Sep | 2 weeks | Carriageway resurfacing |
Easter Road | 11-Sep | 3 weeks | Carriageway resurfacing and minor footway works |
Links Place | 23-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |
Pilrig Street | 29-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |