Minutes of the Community Councils Together on Trams/Trams Team meeting on Thursday 10 March 2022 at 5:30pm, at Trams project compound (165 Leith Walk)
Actions and decisions are red italic. ‘TT’ means ‘Trams Team’. Names are mostly abbreviated to initials.
0 Summary of actions
3.1 | TT to issue dashboards in time for review by CCTT before monthly meetings |
3.1.1 | CCTT (MB) and TT to discuss issues with Gayfield Square traffic offline |
3.2.1 | TT to include dates of updates on all future iterations of map showing completion dates |
3.3.1 | TT to take action about dangers at the substation works near the Trams project compound |
3.4.1 | CW to provide data answering the queries about claims at the next meeting |
3.5 | RA/TT to add date current map of crossings was prepared, and use consistent colours for crossing-types. BR to then publish this map on LCCC, LHNCC, NTBCC websites. |
3.5 | TT to investigate improvements to crossing near Playhouse, and ways to make cyclists walk when using it. |
3.7 | TT to review signage at Constitution St/Ocean Drive advising that Ocean Terminal can’t be accessed via Ocean Drive. |
3.7 | TT to provide ‘look-aheads’ about traffic management changes |
3.8 | CW to provide monthly updates (with data) on business health |
3.8 | CW to advise total amount of business support disbursed. |
3.10 | CCTT (HT) and TT to discuss TT’s meetings with other groups outwith monthly CCTT/TT meetings |
4.1 | future agendas to have an ‘observations’ item |
4.7 | HT and RA to discuss signage on Leith Walk |
5.2.1 | RA/CW to provide written response in the next few days, CCIng this to BR so he can complete minutes |
5.2.1 | RA to escalate the issue raised by JM |
5.2.2 | RA/CW to provide written responses in the next few days, CCIng this to BR so he can complete minutes |
6 | RA and HT to meet next Friday to register of post-project measures |